Parking Lot Repairs

Making the Hole-y Whole Once Again!

We will be having all of the Holy Family parking lots repaired/repaved/resealed/re-striped (depending on area) during the weekdays between May 26-June 11, weather permitting. If weather interferes, the schedule could be extended. The work will be done in stages to permit limited access to the church and school. If cones or tape are blocking off sections of the lot, please do not go beyond or park in them. We will need the lots available for the work to proceed.

Tentative Paving Schedule:

  • May 26-27: Full-depth repairs to part of the west driveway by DAC & front Daisy Lane Lot. This should have little effect on traffic or parking.
  • June 1–4: Repave and stripe driveway by In Heavens Eyes (IHE); Repave and stripe east lot between parish office building (POB) and IHE; Repave and stripe south end of the lot by playground & HFS entrance.
  • June 7 – 11: Seal and stripe the lot between the POB & church; Seal and stripe the lot between the cafeteria and Daisy Lane; Seal and stripe the back lot by cafeteria and Marchino Hall

Subscribe

RSS Feed

Archive


Access all blogs

Subscribe to all of our blogs